Carrington Street
January 11, 2021A Frames Bankside Yard
August 11, 2021
Brierley Hil
Name: Brierley Hill
Product used: A-Frames
Location: Brierley Hill, West Midlands
Project Information Due to the height and nature of this single-sided in-situ wall pour, greater loading upon the formwork needed to be taken into consideration. When designing and using an A-Frame system, cast-in anchors are strongly recommended as they can cope with the tension load at the base. On this project, loading was initially up to 125kN per anchor, however, due to changing site requirements, the base slab was cast without the anchors meaning that a new solution need to be found.
Post-drilled resin anchors where the only viable option, however these were not able to take the 125kN load. The Ischebeck Titan Technical team reviewed the design to reduce the load upon the anchors at the base of the A-Frame. This was done in 2 ways;
• reducing the pour rate to 800mm per hour
• adding in a third frame to each panel section
The redesign took the tension load down to 89kN, which was a load that the resin anchors could accommodate. Ischebeck Titan also supplied NOEtoplarge formwork panels to this project – they provide a good concrete finish, are simple and fast to assemble and have a high capacity to cope with single-sided formwork when used in conjunction with the A-Frame.